Capacity Planning - 2
PERT calculations helps us to calculate the tasks on how much time it took to complete. On further tasks how much time it is going to take to complete. In a project an event or task can be codified and put into the timeboxed event. With the previous resource how much time it took same can be calculated with the future event called as forecasting.
Not only forecasting also can be utilized to provide managers
information how their team performing in each tasks also the report can be used
to compare with the other teams.
But there is a challenge that how to complete all the tasks
within the time. Here comes our another star CPM, Critical path method.
Think about you’re making a biryani at your home, for
example, Saraswathi, Nisha, Gomathi are helping to prepare biryani
Saraswathi cuts vegetable and grind masala
Nisha goes out and bring oil
Gomathi going to prepare the biryani
So plan is this
1st activity cut the vegetables 2 hours, 2nd
activity grinding masala1 hour, 3rd arrange the dry masala 1 hour, 4th
activity going to shop 2 hours, 5th activity prepare biryani which
takes 1 hour
Start, 1st, 2nd, 3rd and 5th,
finish in one line
Start 4th, 5th in one line, finish in one line
2nd path has 2+1=3 hours
So 5 hours is in critical path
Why we need to analyze critical path?
Imagine everyone in above scenario is busy, some one wants
to delay, who can delay or which tasks can delay. If Total hours of 5 hours, in
this Buying oil can be delayed probably Nisha can go to the market after an hour
also. There will be no issues in preparing biryani on time.